{standard_header_image:alt_text}

Christophe Harbour Blog

Today’s Construction Update and Progress Report

By Katherine in Community, Marina, Real Estate

Fact Fans! Quick progress report on Christophe Harbour:

18 Private Homes Completed or Under Construction
266,500 Excavated Cubic Yards
25% of marina channel excavated.
774 Feet of Sheet Pile Driven
150 Dock Piles Driven 
2 Finger Pier Pile Caps Poured

The dream is ever closer!

Tags: superyacht marina, christophe harbour